The Department is currently undertaking a risk-based assessment of Alcoa’s application for a further noise approval. This assessment is considering all submissions received during the public consultation period. The Department is finalising its assessment and will report to the Minister for the Environment who will decide whether to grant or refuse the application for a further noise approval.
The Department is reviewing Alcoa’s Wagerup Refinery licence (L6217/1983/1) through a two–stage process. The first stage of the review focused on conditions relating to fugitive dust and mercury emissions, reporting requirements and modernising the licence format.
As a result of the first stage, the Department amended the licence to include new and strengthened regulatory requirements, including:
The amended licence conditions are open to appeal for a 21-day period, with a copy of the amended licence, associated amendment report and guidance for lodging appeals available on the Department’s website.
The Department will commence the second phase of its licence review in due course. This stage of review is expected to focus on licence conditions related to air emissions, surface water and groundwater, and will be advertised for public comment on the Department’s website once available.
The Department is currently assessing two works approval applications for additional infrastructure at the refinery. One application seeks authorisation to construct and operate a new residue storage facility (RSA 10) adjacent to the existing residue storage area at the refinery (W3144/2025/1).
The second application (W3175/2025/1) is to build and operate a Gallium plant within an existing disturbed area at the refinery. The plant includes a separate processing plant connected to the refinery to receive an offtake of gallium–enriched Bayer liquor that will undergo ion exchange to extract up to 100 tonnes of gallium per year.
The Department’s assessment will consider submissions received during the public comment period and those who made a submission will be notified when a decision is made on the applications.
The Department is conducting four assessments relating to Alcoa of Australia Limited’s (Alcoa) Wagerup Alumina Refinery.
Public consultation for all matters has closed.
In 2012, the Minister for the Environment granted Alcoa approval to vary the allowable level of noise from its Wagerup Alumina Refinery from the prescribed standard. The approval was published in the Government Gazette on 29 June 2012.
Appeals lodged against the 2012 approval resulted in amendments, which were published in the Government Gazette on 10 December 2013.
The 2013 approval provides for Alcoa to:
Following submission of the NAP in 2014, the Department released it for public consultation and published a consultation outcomes paper recommending revisions. Alcoa submitted a revised NAP in 2015 addressing the matters.
The 2013 approval had a two-year duration (expiring on 10 December 2015), unless Alcoa applied for a further approval within the first 18 months.
Alcoa lodged an application for a further noise approval with the Minister for the Environment on 5 May 2015. Therefore, the 2013 noise approval continues to have effect until the Minister grants or refuses to grant a further noise approval.
The Minister for the Environment referred the application to the Department, asking that it enquire into and report on a proposed further approval. Alcoa has since submitted supporting documentation and paid the required fee.
The approach to the existing noise approval was extensively considered by the Environmental Protection Authority (EPA) and subject to community consultation and an appeals process. The Department‘s assessment will focus on the practicality, appropriateness and effectiveness of the existing noise approval requirements and will look at exposure reduction strategies, as established by the EPA.